Project Update on the “catch4climate” Research and Development Project!

 

Work on the oxygen tank farm/LOX plant (LOX = Liquid Oxygen) at the CI4C site in Mergelstetten is almost complete. The electrical engineering is expected to be finished by the end of February 2025, ensuring that nothing stands in the way of the planned cold commissioning in March.

The hot commissioning of the Oxyfuel plant is planned for the second half of 2025.

While the shell construction work for the CPU plant (CPU = CO₂ Purification Unit) is progressing in parallel, steel construction work for this plant section is also in full swing.

At the same time, initial work on the outdoor facilities has begun.

Stay tuned for further updates and exciting insights into the project's progress!

15.01.2025